Name Of ProjectName Of ContractorSponsorContractor Sum (₦)Timelines (Completion on Period)Date Of Award Date Of CompletionDetails Of AgreementStage Of CompletionAmount Paid Including 5% Retention(₦)Remarks
2019 Research and Development/Centre of Excellence Intervention: Furnishing Offices for University Centre of Excellence. New Imagination Ventures LimitedFETFUND9 weeks (2months)August 28, 2020Article of agreement, conditions of contract, and Bill of QuantitiesFirst Tranche Released, to the universityFirst Tranche Released, to the university
2019 Research and Development/Centre of Excellence Intervention: Procurement of Fiat Hilux for University Centre of Excellence. Kosam Heritage Global Services LimitedFETFUND9 weeks (2months)August 28, 2020Article of agreement, conditions of contract, and Bill of QuantitiesFirst Tranche Released, to the universityNil
Needs Assessment Project: Construction of Hostel Block “A”Chlez Engineering LtdNeeds Assessment 36 weeks (9months)November 25, 2016Not CompletedNot Completed85% Contractor abandoned site
Needs Assessment Project: Construction of Hostel ‘’B’’ Goal Ummad LtdNAssessmenteeds 34 weeks (8.5months)November 25, 2016Not CompletedStandard conditions of contract with article of agreement, preliminaries and Bill of Quantities65% PROJECT DETERMINED AND REINSTATED Work in Progress
Needs Assessment Project: Procurement and installation of Equipment for Department of Physiology QualityTon Group Nig LTDNeeds Assessment4 weeks (1months)January 27, 2020September 2020Article of agreement, conditions of contract, and Bill of Quantities preliminaries and Bill of Quantities100% CompletedCompleted and Handed over
Needs Assessment Project: Procurement and installation of Equipment for Department Anatomy Hachi:Clyn Global LtdNeeds Assessment6 weeksNovember 24th 2020Article of agreement, conditions of contract, and Bill of Quantities100% CompletedCompleted and Handed over
Needs Assessment Project: Procurement and installation of Equipment for Department Biochemistry Hachi:Clyn Global LtdNeeds Assessment4 weeksNovember 24th 2020Article of agreement, conditions of contract, and Bill of Quantities100% CompletedCompleted and Handed over
Needs Assessment Project: Procurement and installation of Equipment for Department Architecture.Josem VenturesNeeds Assessment5 weeksNovember 24th 2020Article of agreement, conditions of contract, and Bill of Quantities100% CompletedCompleted and Handed over
Needs Assessment Project: Procurement and installation of Equipment for Institute of pollution studies.Ifegrace Ventures LtdNeeds Assessment3 weeksNovember 24th 2020Article of agreement, conditions of contract, and Bill of Quantities85%Work in progress
Fencing of Onne Campus Physical Planning Direct Labour RSUStandard conditions of contract with article of agreement, preliminaries and Bill of QuantitiesWork stopped due to non-payment to contractor
Procurement and Installation of Equipment for Campus Television Studio Arthurson Business Support LtdJAMB6 weeks (2months)July 17, 2019Feb 2020Article of agreement, conditions of contract, and Bill of Quantities95%Completed and Handed over
Construction of Senate Building Vinkkas Nig LtdRivers State Government50 weeks (13months)June 11, 2020Not CompletedStandard conditions of contract with article of agreement, preliminaries and Bill of QuantitiesWork up to Second Floor DeckWork in Progress
Fencing of Ahoada Campus RSU Direct Labour RSUStandard conditions of contract with article of agreement, preliminaries and Bill of QuantitiesWork stopped due to non-payment to contractor
Fencing of Emohua Campus RSU Direct Labour RSUStandard conditions of contract with article of agreement, preliminaries and Bill of QuantitiesWork stopped due to non-payment to contractor
Fencing of Etche Campus RSU Direct Labour RSUStandard conditions of contract with article of agreement, preliminaries and Bill of QuantitiesStandard conditions of contract with article of agreement, preliminaries and Bill of QuantitiesWork stopped due to non-payment to contractor
Construction of Faculty of Clinical Sciences Vinkkas Nig LtdRivers State Government50 weeks (13months)June 11, 2020Not CompletedStandard conditions of contract with article of agreement, preliminaries and Bill of QuantitiesWork up to Second Floor DeckWork in Progress
Construction of Faculty of Basic Clinical Faculty Vinkkas Nig LtdRivers State Government50 weeks (13months)June 11, 2020Not CompletedStandard conditions of contract with article of agreement, preliminaries and Bill of QuantitiesWork up to Second Floor DeckWork in Progress
Construction of Medical Pathology Vinkkas Nig LtdRivers State Government50 weeks (13months)June 11, 2020Not CompletedStandard conditions of contract with article of agreement, preliminaries and Bill of QuantitiesWork up to Second Floor DeckWork in Progress
Physical Infrastructure/ Programme UpgradeNILTETFUND
Academic Staff Training & DevelopmentNil TETFUND
Library DevelopmentNilTETFUND
Conference AttendanceNilTETFUND
Institution Based ResearchNilTETFUND
Project MaintenanceNilTETFUND
ICT SupportNilTETFUND
Entrepreneurship CentreNilTETFUND
Publication of JournalsNilTETFUND
Manuscript DevelopmentNilTETFUND