Name Of Project | Name Of Contractor | Sponsor | Contractor Sum (₦) | Timelines (Completion on Period) | Date Of Award | Date Of Completion | Details Of Agreement | Stage Of Completion | Amount Paid Including 5% Retention(₦) | Remarks |
---|---|---|---|---|---|---|---|---|---|---|
2019 Research and Development/Centre of Excellence Intervention: Furnishing Offices for University Centre of Excellence. | New Imagination Ventures Limited | FETFUND | 9 weeks (2months) | August 28, 2020 | Article of agreement, conditions of contract, and Bill of Quantities | First Tranche Released, to the university | First Tranche Released, to the university | |||
2019 Research and Development/Centre of Excellence Intervention: Procurement of Fiat Hilux for University Centre of Excellence. | Kosam Heritage Global Services Limited | FETFUND | 9 weeks (2months) | August 28, 2020 | Article of agreement, conditions of contract, and Bill of Quantities | First Tranche Released, to the university | Nil | |||
Needs Assessment Project: Construction of Hostel Block “A” | Chlez Engineering Ltd | Needs Assessment | 36 weeks (9months) | November 25, 2016 | Not Completed | Not Completed | 85% | Contractor abandoned site | ||
Needs Assessment Project: Construction of Hostel ‘’B’’ | Goal Ummad Ltd | NAssessmenteeds | 34 weeks (8.5months) | November 25, 2016 | Not Completed | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | 65% PROJECT DETERMINED AND REINSTATED | Work in Progress | ||
Needs Assessment Project: Procurement and installation of Equipment for Department of Physiology | QualityTon Group Nig LTD | Needs Assessment | 4 weeks (1months) | January 27, 2020 | September 2020 | Article of agreement, conditions of contract, and Bill of Quantities preliminaries and Bill of Quantities | 100% Completed | Completed and Handed over | ||
Needs Assessment Project: Procurement and installation of Equipment for Department Anatomy | Hachi:Clyn Global Ltd | Needs Assessment | 6 weeks | November 24th 2020 | Article of agreement, conditions of contract, and Bill of Quantities | 100% Completed | Completed and Handed over | |||
Needs Assessment Project: Procurement and installation of Equipment for Department Biochemistry | Hachi:Clyn Global Ltd | Needs Assessment | 4 weeks | November 24th 2020 | Article of agreement, conditions of contract, and Bill of Quantities | 100% Completed | Completed and Handed over | |||
Needs Assessment Project: Procurement and installation of Equipment for Department Architecture. | Josem Ventures | Needs Assessment | 5 weeks | November 24th 2020 | Article of agreement, conditions of contract, and Bill of Quantities | 100% Completed | Completed and Handed over | |||
Needs Assessment Project: Procurement and installation of Equipment for Institute of pollution studies. | Ifegrace Ventures Ltd | Needs Assessment | 3 weeks | November 24th 2020 | Article of agreement, conditions of contract, and Bill of Quantities | 85% | Work in progress | |||
Fencing of Onne Campus | Physical Planning Direct Labour | RSU | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Work stopped due to non-payment to contractor | ||||||
Procurement and Installation of Equipment for Campus Television Studio | Arthurson Business Support Ltd | JAMB | 6 weeks (2months) | July 17, 2019 | Feb 2020 | Article of agreement, conditions of contract, and Bill of Quantities | 95% | Completed and Handed over | ||
Construction of Senate Building | Vinkkas Nig Ltd | Rivers State Government | 50 weeks (13months) | June 11, 2020 | Not Completed | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Work up to Second Floor Deck | Work in Progress | ||
Fencing of Ahoada Campus | RSU Direct Labour | RSU | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Work stopped due to non-payment to contractor | ||||||
Fencing of Emohua Campus | RSU Direct Labour | RSU | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Work stopped due to non-payment to contractor | ||||||
Fencing of Etche Campus | RSU Direct Labour | RSU | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Work stopped due to non-payment to contractor | |||||
Construction of Faculty of Clinical Sciences | Vinkkas Nig Ltd | Rivers State Government | 50 weeks (13months) | June 11, 2020 | Not Completed | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Work up to Second Floor Deck | Work in Progress | ||
Construction of Faculty of Basic Clinical Faculty | Vinkkas Nig Ltd | Rivers State Government | 50 weeks (13months) | June 11, 2020 | Not Completed | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Work up to Second Floor Deck | Work in Progress | ||
Construction of Medical Pathology | Vinkkas Nig Ltd | Rivers State Government | 50 weeks (13months) | June 11, 2020 | Not Completed | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Work up to Second Floor Deck | Work in Progress | ||
Physical Infrastructure/ Programme Upgrade | NIL | TETFUND | ||||||||
Academic Staff Training & Development | Nil | TETFUND | ||||||||
Library Development | Nil | TETFUND | ||||||||
Conference Attendance | Nil | TETFUND | ||||||||
Institution Based Research | Nil | TETFUND | ||||||||
Project Maintenance | Nil | TETFUND | ||||||||
ICT Support | Nil | TETFUND | ||||||||
Entrepreneurship Centre | Nil | TETFUND | ||||||||
Publication of Journals | Nil | TETFUND | ||||||||
Manuscript Development | Nil | TETFUND |