Name Of Project | Name Of Contractor | Sponsor | Contractor Sum (₦) | Timelines (Completion on Period) | Date Of Award | Date Of Completion | Details Of Agreement | Stage Of Completion | Amount Paid Including 5% Retention(₦) | Remarks |
---|---|---|---|---|---|---|---|---|---|---|
Years 2016/2018 ICT Support: Training of Academic and none Academic staff on ICT | Fozy Global Nig Ltd | TETFUND | 10 Days | January 13, 2020 | Article of agreement, conditions of contract, and Bill of Quantities | Awaiting Release of First tranche | Delay due to aborted tender on website development | |||
Years 2016/2018 ICT Support: Remodeling of the University Website | Tenece Professional Services Limited | TETFUND | 4 weeks (1month) | August 28, 2020 | Article of agreement, conditions of contract, and Bill of Quantities | First tranche released to the university | ||||
Academic Staff Training & Development | Nil | TETFUND | ||||||||
ICT Support | Nil | TETFUND |