Name Of Project | Name Of Contractor | Sponsor | Contractor Sum (₦) | Timelines (Completion on Period) | Date Of Award | Date Of Completion | Details Of Agreement | Stage Of Completion | Amount Paid Including 5% Retention(₦) | Remarks |
---|---|---|---|---|---|---|---|---|---|---|
2019 Special High Impact Intervention: Construction of Faculty of Arts and Humanities | UYK Nigeria Ltd | TETFUND | 44 weeks (11months) | June 2, 2020 | Not Completed | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Block work to lintel level | Work in Progress | ||
2019 Special High Impact Intervention: Construction of Faculty of Social Science | MNM Construction and Engineering Services Ltd | TETFUND | 44 weeks (11months) | June 2, 2020 | Not Completed | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Block work to lintel level | Work in Progress | ||
2019 Special High Impact Intervention: Construction of Faculty of Education | Marainiya Ventures Ltd | TETFUND | 44 weeks (11months) | June 2, 2020 | Not Completed | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Block work to lintel level | Work in Progress | ||
2019 Special High Impact Intervention: Supply and Install HP Desktop Computers | UYK Nigeria Ltd | TETFUND | 44 weeks (11months) | June 2, 2020 | Standard conditions of contract with article of agreement, preliminaries and Bill of Quantities | Contractor to Mobilize to Site |